MSD
CONSTRUCTIONS Pvt. Ltd.
Mumbai - 09
26th February, 2019
To
The Project Manager
MSD Pvt. Ltd.
Mumbai
Subject : Report regarding the progress of construction.
Sir
I am hereby submitting a short report about the progress of
construction of E & TC Dept. building.
The construction work of this building in the month of August
2018. It is expected to be completed in the month of April 2019
During the last 5 months 40% work has been completed, which
is way behind target.
The following suggestions should be taken into consideration
for the completion of the building construction before given deadline.
1. The laborer
should be increased by 25%
2. The cement
should be supplied on time
3. The
payments of the material should be approved without delay
If the given suggestions are followed the project will be
completed before the deadline.
Thanking you
Yours faithfully
Sign
Site Engineer
(MSD Pvt. Ltd.)