Progress Report regarding the progress of Construction



MSD CONSTRUCTIONS Pvt. Ltd.
Mumbai - 09

26th February, 2019

To
The Project Manager
MSD Pvt. Ltd.
Mumbai

Subject : Report regarding the progress of construction.

Sir

I am hereby submitting a short report about the progress of construction of E & TC Dept. building.

The construction work of this building in the month of August 2018. It is expected to be completed in the month of April 2019

During the last 5 months 40% work has been completed, which is way behind target.
The following suggestions should be taken into consideration for the completion of the building construction before given deadline.

1.    The laborer should be increased by 25%
2.     The cement should be supplied on time
3.     The payments of the material should be approved without delay
If the given suggestions are followed the project will be completed before the deadline.

Thanking you

Yours faithfully
Sign
Site Engineer